Duke Brecon 1 Operations Center Renovation & Addition

Duke Brecon 1 Operations Center Renovation & Addition

This project was a renovation and addition to the Duke Energy Brecon 1 Building.
Our scope included:

  • Complete Interior Demolition of Existing Building
  • 5,200 SF Addition and 6,800 SF Renovation
  • New Plumbing, HVAC, Electric, Security, ALC Controls Throughout
  • New restroom and complete renovation of two existing restrooms
  • New masonry, metal wall panels, and windows at addition
  • New windows in existing building
  • New RTU
  • New offices, training rooms, and locker rooms
  • New Eating Area including new appliances and casework
  • New polished concrete, ceramic tile, carpet, and LVT floors

The project was completed on time by July 31, 2023.

Architect: BHDP Architecture

Mechanical Engineer: HAWA Engineers

Structural Engineer: Schaefer, Inc.

Civil Engineer: Civil & Environmental Consultants, Inc.

  • Client Duke Energy
  • Date May 31, 2023
  • Tags Commercial